               Methodology for deploying Microsoft Dynamics AX is divided into the following phases:

S. NO
Phase
Tasks during phase
1
Diagnostics
  • Evaluate a customer's business processes and infrastructure
  • Prepare a proposal
2
Analysis
  • Analyze the current business model
  • Produce a gap/fit analysis
  • Create the requirements documentation
3
Design

Create documents:
  • Feature design
  • Data migration design
  • Test criteria
  • Technical design
4
Development
  • Develop the features
  • Test the features and functions
  • Create and test the user documentation
5
Deployment

  • Set up the production environment
  • Configure the system
  • Migrate data
  • Test the system
  • Train the end-users
  • Bring the system live
6
Operation
  • Resolve pending issues
  • Finalize the user documentation and knowledge transfer
  • Conduct a post-mortem of the project
  • Provide on-going support
These are on-going activities that continue after project close and throughout any future involvement with the client.
7
Optimization
  • Analyze the system to determine how it can be optimized for the best performance based on customer's needs
  • Perform the optimization
  • Carry out testing
The purpose of this phase is to help the customer optimize the benefit they get from the business solution.
8
Upgrade
  • Review the customer's business processes
  • Align the business processes with new functionality
  • Put the systems in place to support the upgrade

For more just go through this link : http://technet.microsoft.com/en-us/library/aa496439.aspx